P01
Acquisition and plot audit
28 controls5 hard0 Smart Home
post-purchase formalities
CP-P01-001Notify the competent municipality of the property acquisition / verify the IN-1 filing obligationT0101 · Notarial deed and acquisition document setformal
Timingno later than the deadline arising from current law after acquisition
OwnerOwner
Verificationauthoritative current law
Applicabilityconditional
Acceptance criteria
- the correct form and tax treatment are established for every land-use category on the plot
- submission is confirmed, or the absence of an obligation is documented
Required evidence
- official electronic receipt / filing confirmation
- copy of the filed form
- tax-classification note
Failure modes
- missed statutory / filing deadline
- incorrectly applying one property-tax treatment to agricultural land
CP-P01-002Verify the land-and-mortgage-register application after the notarial deedT0101 · Notarial deed and acquisition document setdocumentation
Timingimmediately after purchase
OwnerOwner
Verificationproject specific
Applicabilityalways
Acceptance criteria
- land-register number and application status are known
- plot and owner data match the notarial deed
Required evidence
- notarial deed
- land-register application number / status view
Failure modes
- data error goes unnoticed
- unnecessarily delaying design until the land-register entry is completed
planning
CP-P01-003Extract every MPZP parameter applicable to the plotT0102 · Planning and plot-constraint auditHARD
Timingbefore architectural concept design starts
OwnerArchitect + owner
Verificationauthoritative current law
Applicabilityconditional
Acceptance criteria
- planning-zone symbol and permitted use extracted
- maximum / permitted building footprint extracted
- minimum biologically active area requirement extracted
- development intensity extracted
- maximum / permitted building height extracted
- roof geometry and pitch extracted
- building lines extracted
- road setbacks extracted
- access / traffic-servicing requirements extracted
- garage requirements extracted
- infrastructure protection / reservation zones extracted
- landscape / conservation constraints are recorded in the constraint register
Required evidence
- official extract/map or current planning document
- constraint register
- constraints map
Failure modes
- concept design conflicts with planning rules
- late redesign of the building form
CP-P01-004Verify whether the plot is covered by an MPZP or requires a WZ decisionT0102 · Planning and plot-constraint auditHARD
Timingbefore selecting the administrative pathway
OwnerArchitect
Verificationauthoritative current law
Applicabilityalways
Acceptance criteria
- the planning basis has been established unambiguously
- no unnecessary parallel administrative procedure is being run
Required evidence
- designer note
- identified MPZP plan or WZ decision
Failure modes
- unnecessary administrative procedure initiated
- design based on incorrect assumptions
due diligence / legal
CP-P01-005Consistency of plot number, cadastral district, area and land-register data across all documentsT0101 · Notarial deed and acquisition document setaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-006Easements, claims and limited property rights recorded in the land registerT0102 · Planning and plot-constraint auditaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-007Legal and physical access to a public roadT0103 · Project input repositoryaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-008Cadastral boundaries versus the actual fence and occupationT0101 · Notarial deed and acquisition document setaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-009Identify third-party infrastructure crossing the plotT0102 · Planning and plot-constraint auditaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-010Protection zones for utility networks and equipmentT0103 · Project input repositoryaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-011Constraints arising from nearby forest, watercourses, slopes and infrastructureT0101 · Notarial deed and acquisition document setaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-012Landslide / geological assessment where applicableT0102 · Planning and plot-constraint auditaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-013Verify conservation and archaeological protectionT0103 · Project input repositoryinspection
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the inspection is completed before concealment / release to the next stage
- deviations are recorded and closed or formally accepted
Required evidence
- inspection report / checklist
- photographs or measurement appropriate to the control point
Failure modes
- inspection omitted before an irreversible stage
CP-P01-014Verify trees and potential felling restrictionsT0101 · Notarial deed and acquisition document setinspection
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the inspection is completed before concealment / release to the next stage
- deviations are recorded and closed or formally accepted
Required evidence
- inspection report / checklist
- photographs or measurement appropriate to the control point
Failure modes
- inspection omitted before an irreversible stage
CP-P01-015Identify owners/operators of utilities and the roadT0102 · Planning and plot-constraint auditaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-016Repository of all project-input documents with checksums and revision controlT0103 · Project input repositoryaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
site / context
CP-P01-017Photographic baseline of the plot conditionT0101 · Notarial deed and acquisition document setdecision
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- options and assumptions are compared
- the selected option records rationale, cost, schedule impact and multidisciplinary consequences
Required evidence
- decision record
- comparison attachments
Failure modes
- undocumented ad-hoc decision
CP-P01-018Assess heavy-transport accessT0102 · Planning and plot-constraint auditmeasurement
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the measurement was taken using the correct method and instrument
- the result is recorded with unit, date and location
Required evidence
- measurement report
- photograph / source file where available
Failure modes
- decision based on assumption rather than measurement
CP-P01-019Preliminary stormwater-management assessmentT0103 · Project input repositoryaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-020Preliminary solar-exposure and shading assessmentT0101 · Notarial deed and acquisition document setaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-021Preliminary noise / road-exposure modelT0102 · Planning and plot-constraint auditaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
CP-P01-022Preliminary location of the house, garden, driveway and technical zonesT0103 · Project input repositoryaction
Timingwithin P01 before the related scope is closed
OwnerScope owner + site manager / relevant discipline designer
Verificationproject specific
Applicabilityrecommended
Acceptance criteria
- the scope is executed in accordance with the current design / specification
- the result is verified by the responsible qualified person before release to the next stage
Required evidence
- task checklist
- photographs / document appropriate to the scope
Failure modes
- no execution evidence or late discovery of a clash
deep execution / QA
DX-P01-001Verify address-numbering path and future service addressT0101 · Notarial deed and acquisition document setHARD
Timingbefore the next stage is released or the element is concealed
OwnerOwner + architect
Verificationproject specific
Applicabilityalways
Acceptance criteria
- requirement checked against the current design / specification
- deviations closed before the next stage
Required evidence
- inspection record
- photo / measurement / drawing appropriate to the item
Failure modes
- defect discovered only after concealment or commissioning
- costly rework or loss of serviceability
DX-P01-002Register access rights for utilities and contractorsT0102 · Planning and plot-constraint auditmeasurement
Timingbefore the next stage is released or the element is concealed
OwnerOwner + architect
Verificationsite measurement
Applicabilityalways
Acceptance criteria
- requirement checked against the current design / specification
- deviations closed before the next stage
Required evidence
- inspection record
- photo / measurement / drawing appropriate to the item
Failure modes
- defect discovered only after concealment or commissioning
- costly rework or loss of serviceability
DX-P01-003Photographic baseline of boundaries, ditches, poles and adjacent surfacesT0103 · Project input repositoryHARD
Timingbefore the next stage is released or the element is concealed
OwnerOwner + architect
Verificationproject specific
Applicabilityalways
Acceptance criteria
- requirement checked against the current design / specification
- deviations closed before the next stage
Required evidence
- inspection record
- photo / measurement / drawing appropriate to the item
Failure modes
- defect discovered only after concealment or commissioning
- costly rework or loss of serviceability
DX-P01-004Verify boundary markers before any fencing workT0101 · Notarial deed and acquisition document setinspection
Timingbefore the next stage is released or the element is concealed
OwnerOwner + architect
Verificationproject specific
Applicabilityalways
Acceptance criteria
- requirement checked against the current design / specification
- deviations closed before the next stage
Required evidence
- inspection record
- photo / measurement / drawing appropriate to the item
Failure modes
- defect discovered only after concealment or commissioning
- costly rework or loss of serviceability
DX-P01-005Legal-constraint matrix with an owner for every riskT0102 · Planning and plot-constraint auditHARD
Timingbefore the next stage is released or the element is concealed
OwnerOwner + architect
Verificationproject specific
Applicabilityalways
Acceptance criteria
- requirement checked against the current design / specification
- deviations closed before the next stage
Required evidence
- inspection record
- photo / measurement / drawing appropriate to the item
Failure modes
- defect discovered only after concealment or commissioning
- costly rework or loss of serviceability
DX-P01-006Cross-check plot data between land register, cadastre, survey and deedT0103 · Project input repositoryhold point
Timingbefore the next stage is released or the element is concealed
OwnerOwner + architect
Verificationproject specific
Applicabilityalways
Acceptance criteria
- requirement checked against the current design / specification
- deviations closed before the next stage
Required evidence
- inspection record
- photo / measurement / drawing appropriate to the item
Failure modes
- defect discovered only after concealment or commissioning
- costly rework or loss of serviceability